An Update From the Contractor

The project is finally under way 

The Building Permit has just been issued - much delayed by engineering and FEMA requirements. We are in what FEMA terms a Velocity Zone (V-zone). This designation dictates that no horizontal member may be below elevation 16-16' above mean sea level (this does not apply to sunbathing). Other restrictions apply: including no living spaces below this elevation and only class 3 materials (resistant to water damage) may be used in this region.

We have been busy tearing down the old structure to prep for reconstruction. I decided for the sake of simplicity and consistency to take down all of the walls as opposed to reusing the front wall and a few interior walls. I was surprised and pleased to find driven wood piles under the existing columns. The slab and foundation are very strong - well above the standard of the day it was built.

The footings are dug and rebar is being tied for the grade beam. I will call for an inspection for Monday (2/5), and hopefully we'll pour concrete that afternoon. The framing crew has glued and screwed a second layer of 3/4 plywood over the existing 5/8" sub-floor. They will be framing the rear deck while the concrete crew gets the foundation out of the ground. After that will be floor framing and steel frame work. I will try to post the structural drawings for the project .... the steel beams required to carry the potential wind stresses are substantial - as is the foundation.

We are pushing for a July 4th completion. This is a very ambitious goal and will be dependent on cooperation with the weather, suppliers, etc., but it is our initial target.

Comments (0)Add Comment

Write comment
You must be logged in to a comment. Please register if you do not have an account yet.

busy
 

Copyright VIPFripp © 2007
Beaufort, SC - (843) 524-1102 - This e-mail address is being protected from spam bots, you need JavaScript enabled to view it
 

 
Joomla Templates by Joomlashack
Joomla Templates and Joomla Tutorial