3/5 - 3/9

This week has been productive. The framing has gone up to the roof and ridge beams and rafters are being set. CdT has a very complicated roof line. I moved the camera back towards the beach to get the entire house in the frame - waves are crashing onto the rocks right behind the camera. The weather has been great, but windy. No-see-ums are back!

Materials are on site for the roof sheathing and the rest of the deck in back. We set the glass block frames on both floors, and the glass block in the kitchen.

The wind and a little bit of rain conspired to make a short day on Friday, but we will again be at it on Saturday to try and get a jump on the week ahead.