Thirteenth Week

4/23 - 4/27

Sorry for the delay in getting this out. I have been out of town for four days, and it is disconcerting how much can go amiss in a short amount of time.

The Port Royal bridge was struck by a barge and has been shut down for a projected three months. Hence, all traffic has been diverted towards the old bridge through downtown Beaufort causing hours long delays. I am trying to reset our labor force for the project to use Saint Helena and Lady's Island residents only, which I hope will be effected by Monday.

So ... the roofing materials were delivered but the roofers have not begun metal installation as yet. Plumbers are continuing their rough-in and we are wrapping up interior framing and blocking details.

Kitchen cabinets are ordered, insulation crews are scheduled and drywall is being bid. Every one in the area is realigning schedules to the new reality of access to the islands.

Comments (0)Add Comment

Write comment
You must be logged in to a comment. Please register if you do not have an account yet.

busy
 

Copyright VIPFripp © 2007
Beaufort, SC - (843) 524-1102 - This e-mail address is being protected from spam bots, you need JavaScript enabled to view it
 

 
Joomla Templates by Joomlashack
Joomla Templates and Joomla Tutorial