7/2 - 7/6 The interior trim crew ran most of the crown, base, window molding and closet shelving. The mirrored closet doors did not arrive until the end of the week so the interior trim is going to run into next week finishing up. Hardwood flooring installation began on the second floor balcony. The electrician placed the circuit breakers and is starting to set out the electrical outlets
so that we can get the permanent service inspection necessary for electrical power connection, which will enable us to set HVAC units and get the house under air conditioning and lights. The tile and marble arrived for the bathrooms. There is quite a bit of material being used in this house - those bathroom showers are big! The exterior painting is continuing at a good pace. Light fixtures and plumbing fixturesare on order and should begin arriving next week. We are pushing hard to get everything wrapped up ... Coeur de Terre is a very active job site.
|