5/7 - 5/11

Traffic is still a problem but everyone is getting used to the delays now. The weather really pummeled us ... the sub-tropical storm (tropical storm Ana) off shore brought pretty high winds making Fripp Island's beach looked like a scene from a Hawaiian surfer movie complete with curling breakers.

We made some good progress this week nevertheless. The roofers began Tuesday and are 75% complete. Exterior trim carpenters are continuing on the cornice, siding, and door trim. Another carpentry crew is completing the framing details on the interior ... radius foyer walls, soffit and deadwood blocking, etc. After another week of this work we should be ready for Rough-in Inspection, which will allow us to move on to insulation and drywall - cresting the ridge.

Comments (0)Add Comment

Write comment
You must be logged in to a comment. Please register if you do not have an account yet.

busy
 

Copyright VIPFripp © 2007
Beaufort, SC - (843) 524-1102 - This e-mail address is being protected from spam bots, you need JavaScript enabled to view it
 

 
Joomla Templates by Joomlashack
Joomla Templates and Joomla Tutorial