6/11 - 6/15 The sheetrock hangers began Monday and finishers were right on their heels. The place looks totally different now - finally taking on the finished contours. The foyer stairs arrived on Wednesday - about three weeks later than originally contracted for, and they are very impressive. It is nice to be able to go up stairs without using a ladder. Soon enough it will be an even easier
elevator ride. The primary task now is to get the drywall finishing out of the way and to get the mess picked up, then on to flooring, tile, and trim on the interior, hand rails, painting and landscaping on the outside. With no further delays we will be at C/O the first week of August. Fripp Island is crowded with visitors now and the weather has been great.
|